147 construction permits granted in YCDC area in H1 Jan

A total of 57 building permits were issued within the boundaries of the Yangon City Development Committee in the second week of January.
In addition, regarding Building Complete Certificate (BCC) applications, 147 construction permits were issued within two weeks.
The building completion certificate (BCC) has been approved for 41 buildings, and the list of 25 buildings that have applied for building permits from four to 17 rooms has been sent to the Yangon Electricity Supply Corporation (YESC).
Endorsements have been sent to related departments, such as one letter to the Fire Services Department, 34 letters to the Engineering Department (Water and Sanitation), and 12 to the Urban Land Planning Department to allow building construction.
When applying for building construction permits, it is necessary to include the Standard Operation Procedure (SOP) to be communicated with the Electricity Corporation by the landowners and licensed contractors for obtaining electricity.
This week, licensed contractors will be invited to a meeting to get the BCC and install electricity meters for the buildings. Yangon Electricity Supply Corporation takes the responsibility of installing the electricity meters. 

Source: The Global New Light of Myanmar

Tags: No tags